Comparing changes to the critical paths between two schedules

  1. Run Properties Mapper A, B, 4, 5
  2. Go to Tools => Select Elements
  3. Tick “Clear Selection First”
  4. From “Select” pick “Data Property”
  5. From “Data Property” pick “Select Activities to review”
  6. In “Text” add “-Yes”
  7. From “Match Text” pick “infix match”
  8. Click Run

     9a. Select all the parents of the selected activities by

    9.b. Unselect clear selection

  1. From “Select” Pick “parents of selected nodes”

    11a. click play multiple times until ….

    11b. You are at the top level WBS

  1. Type “Select” (or any other memorable word) in URL
  2. Reverse select by tick “Clear Selection First”
  3. And tick “Select Inverse”
  4. Then Data property => URL => type “Select”
  5. Click play
  6. Then delete selected elements
  7. Finally play the Hierarchic layout
  8. and “Save as” so you do not lose the old file