Convert a P6 Schedule into an editable Network Diagram.

  1. Open your Schedule(s).
  2. Make sure that the “|” character is not used anywhere in your schedule. 
  3. Make sure the full stop character   “.” is not used in your WBS code as the above characters are used to split your csv files.
  4. Select “Do not show time” and “4-digit year” in the settings.
  5. Run your Batch report “LogicReader” and save the files . Do not change the report names.
  6. Open LogicReader.accde. Select preferable settings and click run. The Converter will then create a *.graphml file.
  7. Open *.graphml file you created.
  8. Open Properties Mapper and apply Mapper A and Mapper B to transfer properties to Nodes (Activities) and Edges (Links).
  9. Play Hierarchical Layout to expand your diagram.
  10.  If you get errors please see the “Common Errors” Video

Ready

Scroll to Top