Note on Microsoft Project (MSP) Usage:
MSP schedules must adhere to high-quality standards and proper planning practices.
Key Considerations:
Date Integrity
MSP can be manipulated to display illogical dates. Rigorous validation is essential to ensure chronological accuracy.WBS/Activity Separation
MSP allows conflating Work Breakdown Structure (WBS) elements with actual activities. Maintain clear differentiation between deliverable-oriented WBS components and task-based activities.Constraint Management
Beware of “invisible constraints” driving activity start dates. These often stem from WBS-related dependencies rather than physical workflow links. Explicitly document such constraints rather than relying solely on predecessor relationships.